From Crisis to Control: Building a More Resilient Campus After Elliott

A dark statue and a large, bare tree are covered in fresh snow against an overcast sky. A curved, empty fountain basin is also dusted with snow in the foreground.

In late 2022, Winter Storm Elliott put our campus to the test. The extreme cold exposed vulnerabilities across critical systems and left us with more than $10 million in damage and disruption. It was a hard lesson, and it became a turning point for Facilities Services.  

Since then, our teams have worked with one goal in mind: make campus more resilient, reduce risk, and protect the student and research experience when severe weather hits (and every day in between.) The results have been clear and measurable. The year after Elliott, losses dropped drastically. This year, they fell again to less than $50,000. That’s at least a 99.5% decrease.  

That progress did not come from a single fix. It came from a disciplined, year-over-year effort to strengthen systems, improve readiness, and build accountability. 

Building resilience into systems and daily operations 

One of the behind-the-scenes ways we’ve made improvements is by increasing redundancy where it matters most, including improvements at the steam plant, and expanding our ability to respond with in-house staffing and equipment so we are not relying on contractors for every urgent need. We also implemented constant overwatch during cold weather events, including proactive after-hours walk-through inspections of unoccupied buildings to detect leaks early and prevent system failures. That also includes steps like shutting down chillers as equipment approaches freezing conditions and keeping water moving through vulnerable pumps to prevent freeze-ups. 

We have also made targeted, practical modifications to facilities based on lessons learned. In some areas, even construction details were adjusted, such as raising sheet rock height to avoid damage from water from being wicked up from the floor. Across teams, foremen now use checklists that are signed and turned in, creating real accountability and ensuring preventive actions were completed on time. 

At the same time, we continue to add valves and leak detection sensors that will integrate with building automation systems so problems can be detected sooner and addressed faster. 

A campus-wide weather response plan, designed for reality 

One of the biggest shifts has been moving from reactive repairs to proactive planning. We have worked carefully and creatively to craft a weather response plan focused on protecting equipment and minimizing downtime during extreme events. Part of that work involves developing a building-by-building shutdown sequence for water systems. 

This process is more complex than it sounds. Many spaces cannot simply be turned off, especially research buildings and other critical operations. We are working directly with customers across campus to ensure research can continue where it needs to, while still reducing risk wherever possible. This approach is in great need of expansion across campus, and we are actively building toward it. 

Keeping campus moving 

This year, the difference was not just measured in repair costs. We had zero loss of class time due to facilities issues. Any loss of classroom time that did occur was not caused by building conditions or infrastructure failure. That outcome reflects the focus on preparation, early detection, and coordinated response. 

Lessons learned and improvements made 

Elliott exposed weak spots across systems, including issues as basic as water lingering in fire suppression lines. Those low points became reference points. We learned from them, documented them, and systematically reduced the risk of repeat failures. 

As extreme low temperatures become more common, we are adapting and overcoming, focused on a campus that is ready for the next event instead of being surprised by it. 

What comes next 

We are not stopping with the gains already made. Several initiatives are underway to push resilience further: 

  • Advanced detection and control: We are expanding building automation monitoring so we can detect issues earlier, adjust set points, and use data to drive better decisions. Today, we can change set points globally on one system and are working toward that capability across all systems. 
  • Real-time leak detection and response: Smart sensors in critical areas detect leaks the moment water is present, while flow monitors flag unusual usage that may indicate a hidden issue. These systems communicate directly with shut-off valves, allowing water supply to be automatically stopped where feasible to help prevent further damage across campus. 
  • Staffing for true 24/7 coverage: We want to build out second and third shift capacity so monitoring and walkthroughs can continue after hours, especially overnight. Funding is the limiting factor, but the need is clear. 
  • Steam plant continuity: Three years ago, rolling blackouts triggered cascading stress on systems, including a failure tied to the backup generator. Those issues have been corrected, and we now have a backup plan for the backup plan. Our next goal is a battery system that can bridge the gap between an outage and generator start-up. 
  • HVAC cold-weather protection: We are piloting low viscosity fluids in HVAC systems to determine whether they improve cold-weather performance, with plans to expand if results meet expectations. 
  • Environmental response capability: We have hired two environmental technicians to strengthen early detection and speed clean-up when issues occur. 

We are also building these lessons into the future. Many campus facilities were constructed for a different version of this climate. We are modifying older buildings where we can, and we are incorporating safeguards into design standards for new construction so future projects start with resilience built in. 

The people behind the progress 

The most powerful part of this story is the human one. When winter weather hits, there is no siloed thinking and no “that’s not my job” mentality. Facilities Services staff are here around the clock, moving wherever the need is greatest. 

During Winter Storm Elliott, a chain reaction of systems started failing on Christmas Eve. The required shift away from natural gas, along with rolling outages, created additional strain that contributed to the longer-term steam plant outage. It took a full team effort to stabilize the situation, and they got through it. Steam plant staff came in overnight and stayed for hours when they were not even scheduled. People stepped up because campus needed them. 

A stronger campus, built on experience 

Winter Storm Elliott was a defining moment. It revealed where we were vulnerable. It also sparked a commitment to do better, year after year, system by system, building by building. The losses have dropped dramatically, disruptions have been reduced, and the campus is more prepared than it has ever been for severe cold. 

We cannot control the weather. We can control how ready we are for it.