UTK Facilities Services Planning and Design is overseeing the demolition of the UT Warehouse to make way for a new two-tiered surface parking lot expected to provide over 700 spaces when complete.
June 2025 status update:
- Space Management is working closely with the building’s occupants to identify suitable relocation spaces.
- Affected units include Parking Services, Surplus, Facilities Services, and Athletics.
- Units will be relocating during the month of June for demolition of the UT Warehouse to begin in July.
April 2026 status update:
- 3/9: Mass demolition of building structure completed.
- 3/11 – 3/20 : Electrical panels installed; dock leveler concrete infill completed; area drain installed
Ongoing: Electrical trench work and south storm drain line work began; Jones Brothers Construction
mobilized for erosion control and site prep - On schedule for completion 08 June